The revised Carolina Springs Town Center plan puts a 50,887-square-foot grocery store at its center. The Town Council approved it Nov. 17 after a hearing.
Updated Nov. 20: the Town Council approved the amendment at the Nov. 17 hearing. The grocer is still unnamed. Our story on the decision has what the developer told the council.
A revised plan for the Carolina Springs Town Center would build a 50,887-square-foot grocery store on the town center site at Carolina Springs Boulevard and Old Holly Springs Apex Road. The Holly Springs Town Council holds a public hearing on it at 7 p.m. Tuesday at Town Hall, 128 S. Main St.
The change cuts the center’s commercial space by about 25,000 square feet. Town staff recommend approval. The details come from the staff report in the council’s Nov. 17 agenda packet.
What the new plan includes
The site is 20.37 acres at 100 Carolina Center Way. It is the commercial heart of the Carolina Springs planned unit development, which allows up to 1,700 homes. Shenandoah Homes is the applicant.
The amended plan calls for:
- a grocery store of 50,887 square feet
- 52,425 square feet of other commercial space
- two outparcel lots along Old Holly Springs Apex Road, each needing its own plan later
- 1.10 acres of pocket parks, with shaded seating, playgrounds and a dog park at the south end
- public art in the open space on the corner
- 413 parking spaces, the most the town’s rules allow for the site, with 30 electric vehicle chargers and 55 bike spaces
Buildings would stand about 30 feet tall. The grocery store’s loading dock would sit at the back, screened from the road, the staff report says.
Why the plan changed
The applicant told the Planning Board on Oct. 27 that two grocery chains interested in the site said the approved layout blocked the view of the store. The new design moves the store toward the back center of the site to open sight lines from the road. The draft Planning Board minutes record the explanation.
The applicant also switched grocery brands, the minutes say. The new store uses a different parking layout. Neither the staff report nor the minutes name the grocer.
The applicant’s consultant told the board that these businesses have committed to the center:
- two fast casual restaurants
- a sit-down restaurant
- a veterinary clinic
- a nail salon
- a dental studio
Less commercial space, and a staff caveat
The amendment cuts commercial space from 135,393 square feet to 110,312, according to the staff report. The planned unit development requires 120,000 square feet in the town center. The developer would move the missing 10,000 square feet to the neighborhood’s Innovation District, which would then need at least 210,000 square feet. The rules allow that transfer.
Staff found the amendment consistent with the town’s plans. But the report also says the new design is “overall less favorable” than the approved one. It is more reliant on cars, staff wrote, with fewer buildings along Carolina Springs Boulevard and Old Holly Springs Apex Road. The gaps become open space and extra parking.
The Planning Board recommended approval 7-1 on Oct. 27. Board member Van Crandall raised the loss of commercial space and asked whether the traffic review reflected growth in the area, including the start of construction at Veridea, the large development planned across the line in Apex. The town’s engineer said the traffic memo found no change from the original study.
Homes are tied to the shops
An agreement between the town and the developer links new homes to commercial building, so the neighborhood does not end up as housing alone. The staff report sets out these limits on building permits:
| Homes allowed | Commercial milestone |
|---|---|
| Up to 425 | Before plans for 20,000 square feet are approved |
| Up to 850 | 20,000 square feet built |
| Up to 1,015 | 40,000 square feet built and plans for 20,000 more approved |
| All 1,700 | 60,000 square feet built |
The town has issued 670 home building permits in Carolina Springs so far, and 596 homes have certificates of occupancy, the report says. The applicant pursued the amendment partly so Lennar’s home building would not stop while the grocery choice was pending, the Planning Board minutes say.
Part of the site was once set aside for a fire station. The town put Fire Station 3 on Cinder Station Road instead, so that land returns to the town center.
What it means for you
- You can speak Tuesday, but it works like a court hearing. The council’s decision is quasi-judicial. It has to rest on sworn facts and evidence, not opinion. Speakers are sworn in and can be cross-examined.
- Neighbors’ concerns so far came at the developer’s Oct. 29, 2025, neighborhood meeting: screening between the shops and homes, traffic on Old Holly Springs Apex Road, the timeline for clearing the south side, and light spilling onto nearby lots.
- No opening date has been set. If the council approves, the developer can move on to construction plans. The outparcels need their own plans before anything is built there.
- The full agenda, staff report and plan sets are on the town’s meeting page for Nov. 17.
Have your say